AL Report Card - 04/30/10 - ID#415

Site Information
Date of Site Visit: 
Sat, 05/01/2010
Enforcement Office: 
Site Name: 
Dale CR 59 at East Fork Choctawhatchee River
Site Location: 
Bridge at Dale CR 59 and E. Fork Choctawhatchee River
County/Municipality: 
Dale - nearest town Midland City, Alabama
Project Owner: 
Dale County Road Department
Contractor/Emergency #: 
Derek Brewer 334-7745875
Type of Project: 
Roadway (DOT)
Weather During Visit: 
Partly Cloudy
Rain in prior 24 hours: 
NO
Waterbodies Onsite: 
East Fork Choctawhatchee River
Drains Into: 
Choctawhatchee River
Location: 
AL31° 22' 26.76" N, 85° 31' 20.28" W
1. Registration/Information Posting | 2. Stormwater Appearance
1d. Comments: 
Technically this is a maintenance project (an emergency bridge repair project) and does not I believe require CSW permit registration although County Engineer Derek Brewer indicated that they had to obtain permits.
3. Construction Entrance/Exits | 4. Perimeter Controls
3a. Is there enough stone, gravel, or stabilizing material to cover the entrance/exit?: 
YES
3b. Are construction materials and equipment being stored away from the entrance/exit?: 
YES
3c. Is the road free from dirt tracked from the site?: 
YES
3d. Is the construction entrance/exit free from flowing dirty water?: 
YES
4a. Are perimeter controls present?: 
NO
4f. Comments: 
Controls not of much use for streambank portion of project. Bare ground where work was complete had been seeded and fertilized.
5. Storm Drain and Inlet Protection | 6. Soil Stabilzation and Cover
5a. Are storm drains and inlets protected and in good repair?: 
NO
5c. Comments: 
At the first visit on May 1 there was a pipe that directed discharge to an unarmored bare soil area near the river bank. This was subsequently corrected - see May 5 report for this site.
6a. If areas have been inactive for more than 14 days are they stabilized and in good repair?: 
YES
6b. Are completed phases of the site seeded for permanent vegetation?: 
YES
6d. Is the site free of rills or other major erosion on slopes or soil stockpiles?: 
YES
8. Outlet Protection | 9. Encroachment on Waterbodies
8a. Are outlets armored with stone or otherwise protected and in good repair?: 
NO
8c. Comments: 
One drain pipe lacked armoring.
9a. Is vegetation adjacent to waterbodies intact?: 
YES
9b. Are waterbodies and adjacent buffers free of built structures, including basins and traps?: 
YES
General Comments | Photos
10. General Comments: 
In addition to the bridge repair the Dale County Road and Bridge Department created an access point for recreational users - see May 5 report for more details.
AL Report Card - 04/30/10 - ID#415
AL Report Card - 04/30/10 - ID#415
AL Report Card - 04/30/10 - ID#415
AL Report Card - 04/30/10 - ID#415
AL Report Card - 04/30/10 - ID#415
AL Report Card - 04/30/10 - ID#415
Enforcement Log
Enforcement Log Notes: 
See May 5 followup site report